QUESTION 91Your lead engineer estimates that a work package will most likely require 50 weeks to complete. It could be completed in 40 weeks if all goes well, but it could take 180 weeks in the worst case. What is…Continue Reading →
mavisMarch 12, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (71-80)
QUESTION 71Your customer signed off on the requirements document and scope statement of your video game project last month. Today she stated she would like to make it an interactive game that can be played on a television and on…Continue Reading →
mavisMarch 12, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (61-70)
QUESTION 61You have been appointed project manager for a new project in your organization and must prepare a project management plan. You decide to prepare a WBS to show the magnitude and complexity of the work involved. No WBS templates…Continue Reading →
mavisMarch 4, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (31-40)
QUESTION 31Project management processes describe project work, while product-oriented management processes specify the project’s product. Therefore, a project management process and a product- oriented management process______________.
mavisMarch 4, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (21-30)
QUESTION 21Because your project is slated to last five years, you believe rolling wave planning is appropriate. It provides information about the work to be done______________. A. Throughout all project phasesB. For successful completion of the current project phaseC. For…Continue Reading →
mavisMarch 3, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (11-20)
QUESTION 11You are managing a project in an organization is characterized by with rigid rules and policies and strict supervisory controls. Your project, sponsored by your CEO who is new to the company, is to make the organization less bureaucratic…Continue Reading →
mavisMarch 3, 2014PMI Dumps, PMP DumpsComments Off on 2014 Latest Pass4sure&Lead2pass PMI PMP Dumps (1-10)
QUESTION 1You work for a software development company that has followed the waterfall development model for more than 20 years. Lately, a number of customers have complained that your company is taking too long to complete its projects. You attended…Continue Reading →